Cushaling Wind Farm
Sector
Energy Power & Renewables
Client
Confidential
Duration
36Months
Region
Offaly
Cushaling Wind Farm
Suir Engineering successfully delivered the civil and electrical design, construction, and installation works for the 110kV AIS substation and 33kV substation, including grid transformer installation, two (2 no.) 110kV grid routes, wind farm collector circuit cabling design and installation, and OHL LCIM tower installation, all in compliance with Eirgrid functional specifications.
The project comprises three key components:
The Wind Farm Substation, featuring both the EirGrid and Independent Power. Producer (IPP) sections.
A 33kV Cable Route connecting the Substation to the Wind Farm Interface Point.
The Wind Farm Site, the powerhouse of this green energy initiative.
Scope of work
Electrical Services Installation
- Grid cable installation.
- Substation fitout.
- Site MV and FO cable installation.
- WTG foundation and counterpoise earthing.
Civil Services Installation
- Substation earthing work.
- Substation buildings.
- Substation plinths.
- Substation security fencing.
- 0.5km 110 kV ducting connecting Buffy to Knockranny.