Clonfad Solar Farm
Sector
Energy Power & Renewables
Client
Statkraft
Duration
18 Months
Region
Westmeath
Scope of work
Electrical Installation
- DC Cable & Connector System, module-to-module connection, combiner boxes to inverters if applicable including cable containment, mechanical protection and environmental protection
- DC Stringing arrangement & DC Cable sizing
- Inverter layout design
- LV AC Cable & Connector System between inverters and LV:MV Transformers stations
- AC Distribution Boards / Panels
- LV:MV Transformers including buildings/enclosures/environmental protection & electrical protection & switchgear
- MV AC Cable between IPP substation 33kV Switchgear and LV:MV Transformer Station
- DC and AC cable above ground mechanical and environmental protection
- DC and AC cable below ground mechanical and environmental protection
- MV AC Cable between each LV:MV transformer stations: mechanical and environmental protection, identification tape/plates
- PV Plant Site Wide Earthing/Equipotential Bonding System including IPP substation 33kV
- Auxiliary Power Supplies
- PV Plant site-wide surge protection