Botley 100MWh Battery Energy Storage System (BESS)
Suir Engineering delivered the Botley 100MWh Battery Energy Storage System, located near Southampton in Botley. The project comprises the planning discharge, design, procurement, installation, commissioning, and energisation of the facility, which includes a 1.7km grid connection traversing public highway, SPOC areas, and private lands.
The delivery of the grid connection presented significant logistical and legal complexity, requiring the execution of multiple legal easements and close coordination to ensure the design fully complied with SSEN (Scottish and Southern Electricity Networks) specifications.
Construction commenced in August 2023 with cut and fill works to establish the site footprint. Following achievement of design levels and compaction testing, foundation works for the battery infrastructure were undertaken, with a total of 252 in-situ concrete foundations installed. This also included associated cable ducting for electrical infrastructure, as well as the installation of hardstands for craneage setup and offloading operations.
The project team has since installed all HV, LV, DC, and control cabling across the site, with termination and testing works now well underway. The installation and connection of over 6,000 lithium-ion batteries is also in progress.
The system comprises more than 6,000 lithium-ion battery modules manufactured in Korea and 18 no. 3.5MVA transformers manufactured in Germany.